Rough schedule
Beam operation could be interrupted after each week to break for summer shutdown. In that case about 3-5 days to be added after summer shutdown for system restart
Week 1: Injector set-up & RF restart
Injector: Gun conditioning, beam to I1D, emittance optimization and optics match, flat top increase
XTL: Intelock set (incl. ZTS), Systems switch-on, RF tuning
XTDs: open
Week 2: XTL restart
Injector: flat top increase
XTL: RF tuning cont., Beam to TLD, RF set-up with beam, orbit optimisation, optics match after L3, compression set-up and check with TDS BC2 and THz
XTDs: open
Alternate A: Work in XTD4 (SASE3) continues
Week3: SASE2 restart and optimize
Injector: flat top inrease
XTL: bunch # increase
SASE2: Interlock set, beam to T5D, BBA, orbit optimisation, SASE search 9 keV
SASE2: SASE tune, wavelength range, gain curve
SASE1/3: XTDT2/4/9/10 stay open
Week4 (after closure XTD4): SASE1/3 restart and optimize
SASE1/3: Interlock set, beam to T4D, BBA, orbit optimisation, SASE search 9 keV
SASE1: SASE tune, wavelength range, gain curve
SASE3: pointing
Alternate B: Work in XTD4 (SASE3) finished
Week3: SASE restart
Injector: flat top inrease
XTL: bunch # increase
SASE2: Interlock set, beam to T5D, BBA, orbit optimisation, SASE search 9 keV
SASE1/3: Interlock set, beam to T4D, BBA, orbit optimisation, SASE search 9 keV
Week4: SASE optimize
SASE2: SASE tune, wavelength range, gain curve
SASE1: SASE tune, wavelength range, gain curve
SASE3: pointing
XLS Sheet with rough planning:
Word Document describing re-start and operation scenarios
And more detailed planning